A standard small office network installation in Auckland takes 1–3 days. A 5-person office is usually finished in a single day, a 15–20 person office takes 2–3 days, and larger fit-outs are planned in stages so your team can keep working. Below is exactly what each phase looks like and what you can do to make the install go faster.
“The fastest way to slow a cabling install down is to start it before the site is ready. Every day a 20-person office is offline costs you about
,000 in lost productivity.”
How long does a small office network installation take in Auckland?
| Office size | Typical timeline | Notes |
|---|---|---|
| 3–5 person office (6–10 data points) | 1 day | Cable pull, terminate, test, certify |
| 10–15 person office (15–25 points) | 1.5–2 days | Most jobs split across two days |
| 20–30 person office (30–50 points) | 2–3 days | Phased to avoid disrupting the team |
| Large fit-out / multi-floor (50+ points) | 3–7 days | Often runs alongside builders |
What happens at each stage of the install?
- Site survey (1–2 hours), we visit your office, measure cable runs, identify the comms cupboard, and confirm the cable path that minimises wall damage.
- Quote and design (1–3 days), fixed-price quote with a clear cable schedule, usually back to you within 24–48 hours.
- Material prep (same day as install), cable, faceplates, patch panel and rack delivered to site.
- Cable pull (most of day 1), running cable from each desk through walls/ceilings back to the comms cupboard.
- Termination and testing (day 1 evening / day 2 morning), terminating each cable into wall plates and the patch panel, then testing with a certified cable tester.
- Certification and documentation (final hours), generating the test report, labelling everything, and handing over a clear cable schedule.
What factors make the install take longer?
- Building material, concrete, brick or fully insulated walls take longer to pull cable through than standard plasterboard.
- Multi-floor runs, each floor needs its own cable path or fibre link.
- Lots of data points, every additional run adds material and termination time.
- Existing cabling that needs removal, old, unlabelled cabling often needs to come out before the new install.
- After-hours or weekend work, adds time at the front end (planning) but keeps your team uninterrupted.
- Combined services, if we’re also installing CCTV, alarms or access control, expect 1–2 extra days but at significantly lower combined cost.
How can I make my office cabling install go faster?
- Confirm desk locations before the survey, walking through the final office layout once saves return visits.
- Clear access to the comms cupboard, making sure we can get to the rack on day one.
- Decide on extras early — Wi-Fi access points, CCTV, smart-home pre-wire, adding them after install always takes longer than during.
- Choose the right cable for the run. Cat6 for desks, Cat6A for backbone, fibre only where needed.
- Have your IT person on call for switch settings, most cabling installs aren’t blocked by IT, but having someone available speeds up final testing.
Will the install disrupt my team?
Most cable pulling can happen during business hours without affecting the team, it’s just a person running cable through ceilings or walls. The noisier work (drilling, cutting plates, switching off the existing network) is scheduled either at the start of day, lunch, or after hours. We confirm the schedule with you before we start so there are no surprises.
What does an extra day on site cost?
A 3-day install becomes a 7-day install when ceiling tiles aren’t accessible, when parking isn’t pre-arranged, or the comms cupboard is locked when we arrive. We’ve seen single locked-door delays add 2 working days. For a 20-person Auckland office, that’s roughly $20,000 in lost productive hours, sometimes more than the entire cabling job.
Three things you can do this week to cut your install timeline in half:
- Confirm building access (out-of-hours pass, security, parking) the day we book the job.
- Move heavy desks and clear the comms cupboard before our team arrives, not during install.
- Have a single decision-maker on site for sign-off (not a committee).
Get those three right and we’ll usually beat the timeline we quote you.
Frequently asked questions
Can the install happen outside business hours?
How quickly can you start after I sign off the quote?
Will my team have internet during the install?
Do you provide a written cable schedule when you finish?
What if I need an extra data point added later?
Ready for a fixed-price quote you can trust?
Auckland-owned and operating since 2018. Trusted by 100+ Auckland homes and businesses. Same-day service or your call-out is free. 12-month workmanship warranty. $5M public liability cover.
Reviewed by Namra Shah, Founder & Director of Cabling For U. Cabling For U has been delivering certified network cabling, fibre and CCTV installations across Auckland since 2018, installing to TIA/EIA and AS/NZS standards.

